The keys to the first three completed stations on the Metro Tunnel Project – Arden, Parkville and Anzac – have been handed over to Metro Trains in preparation for the tunnel opening this year.
The transfer of management from the builder to the Government is a big milestone in the Metro Tunnel’s completion, The handover marks the moment Victoria’s rail workers can ‘move in’ and start operating and managing the station’s assets and systems, to get familiar with the new stations ahead of day one.
In another big milestone, trains have now travelled more than 100,000km inside the Metro Tunnel – the equivalent of two-and-a-half trips around the Earth’s circumference.
This testing has continued progressively since the first trains entered the tunnels in mid-2023, ensuring equipment and systems are working as designed.
As testing and trial operations continue along the length of the future continuous line from Sunbury to Cranbourne and Pakenham, there will be disruptions on the lines over three days next week – 14, 15 and 17 April.
Crews are also making progress to complete construction on the remaining two stations, Town Hall and State Library, which sit directly underneath Melbourne’s CBD.
The Metro Tunnel includes five new underground stations and will be the biggest upgrade of Melbourne’s train network since the City Loop opened in 1981.